Time schedule and progress monitoring Typical implementation phase schedules are introduced in connection with time schedule development. In the implementation phase, procurement schedules are perhaps the most dictating schedules related to the overall time frame, as equipment supplies and availability of supplier documentation and data impacts all the other technical work. As an example, not